Random files - PNG |

Walls9 viewsOOPS! Ok here's a mistake, somebody nailed a noggin above the stringline while the other guy nail it below- (all 3 noggins should be at the same level) no need to change it but we'll just have to watch these things.
|
|

Site Overview14 viewsProgress as of 9/18/2011.
|
|

16 viewsA sunny day and poisonous berries.
|
|

The Facilities14 viewsAfter a lovely rain, down river from here is a laundry facility, a bathing facility, and a drinking facility -- in fact you may be using all three together at the same time. There are many of these "facilities" locally but some have dried up due to very little rain this month.
|
|

Inside work12 viewsThe other area we're working on is the hardwood floors: the upper bedrooms are completed and the dining room is also planned to be completed by the end of next week. We're also working on the plywood wall covering, and that may be a couple of weeks before that's completed. We're looking at hiring a painting crew & possibly a tile crew for the lower floor. We found a furniture business that'll make the bunk beds for about 10% above our cost and some 40% below the local warehouse, whom he also builds beds for
|
|

11 viewsOne of the upper bedrooms. Still needs windows, trim, paint and electrical, but we're making progress.
|
|

45 viewsWe're making progress in many areas, one is below. The electricians are installing the underground service and the communication cables - both have to be in there own conduits. The PNG power system utilizes 3-240Volt lines unlike our U.S. 2-120Volt lines
|
|

26 viewsThe top floor bedrooms and hallway were sanded last week.
|
|

Last additions - PNG |

32 views1st coat of varnish, trim work should be finished this week.Feb 13, 2012
|
|

29 viewsShower stall tile work still in progress.Feb 13, 2012
|
|

32 viewsKitchen cabinetsFeb 13, 2012
|
|

26 viewsThe veranda, weather permitting, should have the roof trusses and iron on at the end of the week; rain gutters also.Feb 13, 2012
|
|

26 viewsThe top floor bedrooms and hallway were sanded last week.Feb 13, 2012
|
|

31 viewsSome more of the trenching work. Many utility lines and pipes were encountered while digging this up.Jan 16, 2012
|
|

28 viewsThe upper floor is all tongue and grooved hardwood (except the tiled bathroom). The finishing of these floors will begin once all painting and electrical work is completed. Base molding will then be installed.Jan 16, 2012
|
|

32 viewsAs of Friday the tiles are laid in the bedrooms, this hallway and the kitchen. The tiling of the bathrooms on each floor, both walls and flooring will begin this week. The dining room will be the last room tiled.Jan 16, 2012
|
|

|
|
|